Access free live classes and tests on the app
Download
+
Unacademy
  • Goals
    • AFCAT
    • AP EAMCET
    • Bank Exam
    • BPSC
    • CA Foundation
    • CAPF
    • CAT
    • CBSE Class 11
    • CBSE Class 12
    • CDS
    • CLAT
    • CSIR UGC
    • GATE
    • IIT JAM
    • JEE
    • Karnataka CET
    • Karnataka PSC
    • Kerala PSC
    • MHT CET
    • MPPSC
    • NDA
    • NEET PG
    • NEET UG
    • NTA UGC
    • Railway Exam
    • SSC
    • TS EAMCET
    • UPSC
    • WBPSC
    • CFA
Login Join for Free
avtar
  • ProfileProfile
  • Settings Settings
  • Refer your friendsRefer your friends
  • Sign outSign out
  • Terms & conditions
  • •
  • Privacy policy
  • About
  • •
  • Careers
  • •
  • Blog

© 2023 Sorting Hat Technologies Pvt Ltd

Watch Free Classes
  • SSC Notes
  • Downloads
  • What's New
  • SSC JE Exam Pattern
  • SSC CGL Exam Syllabus
  • SSC CGL Exam Pattern
  • SSC CAPF
  • SSC CGL
  • SSC CHSL
  • SSC JE
  • SSC JHT
  • SSC MTS
  • SSC Steno C and D
SSC Exam » SSC Study Materials » Mathematics » Time & Work
scholarship_ssc

Time & Work

This article is an introduction to the concepts of time and work and their key formulas. We will also explain the characteristics of time and work to have a clear understanding of concepts.

Table of Content
  •  

How do we define time? A time span is the amount of time in which any activity is carried out or continues to be carried out. How do we define work? The definition of work is a set of activities designed to achieve a certain goal.

An individual or group’s efficiency and the duration of time needed to complete a task are considered simultaneously in time and work problems. To work means to dedicate effort towards completing a task or delivering a deliverable.

A certain amount of time is required for the completion of a certain task. The rate of work is defined as the amount of work completed per unit time. So, Work  = Rate x Time.

Important time and work formulas

Any work that is happening can be described by the list of some important formulas used in time and work:

  • In an X-day work cycle, if person A completes the work, 1/X is the amount of work they completed in 1 day.

  • In the same way, if person B completes work in Y days, then 1/Y is the number of days they completed in one day.

  • From the above two points, it was established that A and B together could accomplish (1/X + 1/Y) of the work in one day. The work can be completed in X + Y/XY days by A and B working together.

  • The total work done comes from the total time multiplied by the rate of work spent.

  • Work is calculated as 1/time taken.

  • Calculate the time taken by taking 1/rate of work.

  • Throughout efficiency/one-day and work/work rate, the proportionality sign is removed from work cloning and, therefore, is removed from the work rate.

Total Work Done = Number of Days × Efficiency

  • Efficiency is inversely proportional to time.

  • It is the ratio of the number of people who can complete a specific task in W1 to the number of people who can complete the task in W2. When “X” and “Y” work for T1 hours per day in D1 days, while T2 hours per day in D2 days.

M1 ∗ D1 ∗ H1 ÷ W1 = M2 ∗ D2 ∗ H2 ÷ W2

We can also consider the following table for a better understanding of the concepts and for easy calculation:

Number of days required to complete work

Work/Day

Efficiency (%)

N

1/N

100/N

1

1

100

2

1/2

50

3

1/3

33.33

4

1/4

25

5

1/5

20

6

1/6

16.66

7

1/7

14.28

8

1/8

12.5

9

1/9

11.11

10

1/10

10

11

1/11

9.09

12

1/12

8.25

13

1/13

7.69

14

1/14

7.14

15

1/15

6.66

Characteristics of time and work

  • When the amount of work is constant, efficiency is inversely related to the time taken.

  • Statements such as ‘A is three times as good as B,’ mean that A does three times the work as B in the same amount of time. To put it another way, A will take one-third the time that B will take to do the identical task.

The proportion of work done by A and B = 3:1

The proportion of time taken by A and B to complete the work = 1:3

  • A person’s efficiency can be measured by the amount of time it takes an individual to complete a task and how long it takes a group of people to complete a task over the course of a period of time. Individual work can also be measured by the amount of work completed by a group of people over the course of time.

Conclusion

The concepts of time and work are used to calculate the amount of time it takes to accomplish a task and our ability to determine the amount of work we have accomplished. We learned how to determine a person’s efficiency, how long it takes an individual to complete a task, and how long it takes a team to accomplish a task. The level of efficiency is determined by the amount of work completed by individuals over time and the amount of work completed by a team over a specific period. It is possible to know how many tasks a person can complete in a set period of time by looking at their ability to complete them.

faq

Frequently asked questions

Get answers to the most common queries related to the SSC Examination Preparation.

Kishan can accomplish a job in 10 days, and Mohan can accomplish a job in 40 days. If both are working together, find the total days required to accomplish the work.

Answer: Kishan can complete 1/10th of the work in one day, and Mohan can compl...Read full

Explain what the efficiency of work is.

Answer: An individual’s efficiency is their capacity to complete a particular amount of work in a day (express...Read full

Three individuals are capable of completing a piece of work in 24 days, 30 days, and 40 days, respectively. They started the work together, yet C left 4 days before the accomplishment of the work. How long did it take to finish the work?

Answer: The work done in one day by A, B, and C = (1/24 + 1/30 + 1/40) = 1/10. ...Read full

20 ladies can accomplish a task in 16 days. 16 men can accomplish similar work in 15 days. What is the proportion between the limit of a man and a lady?

Answer: Total work that ladies can accomplish in one day = 20 x 16 = 320. ...Read full

Answer: Kishan can complete 1/10th of the work in one day, and Mohan can complete 1/40th of the work in one day.

This means that if both work together in one day, they could complete (1/10) + (1/40) = 5/40 = 1/8th of the work. So, the total time taken by both of them to accomplish the complete work is 8 days.

Answer: An individual’s efficiency is their capacity to complete a particular amount of work in a day (expressed in percentage terms). A person can accomplish a job in two days or, in other words, they can accomplish 50% of the work in a day. Hence, their efficiency is 50%.

Answer: The work done in one day by A, B, and C = (1/24 + 1/30 + 1/40) = 1/10.

C leaves 4 days before accomplishing the work, and that implies just A and B work during the most recent 4 days.

Work completed by A and B in the last four days = 4 (1/24 + 1/30) = 3/10.

The remaining work is 7/10, which was accomplished by A, B, and C in the underlying number of days.

The number of days expected for this underlying work = 7 days.

Hence, the total number of days required to accomplish the work is  4 + 7 = 11 days.

Answer: Total work that ladies can accomplish in one day = 20 x 16 = 320.

Work done in one day by one lady = 1/320.

Total work that men can accomplish in one day = 15 x 16 = 240.

Work done in one day by one man = 1/240.

So, the required ratio of man and lady is 1/240 : 1/320 = 4 : 3.

Crack SSC with Unacademy

Get subscription and access unlimited live and recorded courses from India’s best educators

  • Structured syllabus
  • Daily live classes
  • Ask doubts
  • Tests & practice
Learn more

Notifications

Get all the important information related to the SSC Examination including the process of application, important calendar dates, eligibility criteria, exam centers etc.

SSC CAPF Notifications
SSC CGL – Notification, Exam Date, Selection Process
SSC CHSL Notifications
SSC JE Notifications
SSC JHT Notifications
SSC MTS (NT) Notifications
SSC Steno C and D Notifications
Staff Selection Commission
See all

Related articles

Learn more topics related to Mathematics
Wrong Number

The term wrong number series can be a series of numbers that doesn't obey any sequence and an odd number is present in even sequence.

Working and Sleeping Partners

In this study, the difference between the working partner and the sleeping partner will be described. In addition, it will also provide some examples of working and sleeping partners.

Whole Numbers in Real-Life Situations

All natural numbers and zero collectively make up whole numbers. In this article, we will discuss whole numbers and their application in real-life situations.

Whole Numbers

This article will discuss whole numbers, the properties of whole numbers, and how they are useful in mathematics.

See all
Access more than

15,501+ courses for SSC Exams (Non Technical)

Get subscription

Trending Topics

  • SSC Exam Calendar
  • SSC JE Exam Pattern
  • SSC CGL Exam Syllabus
  • SSC CGL Exam Pattern
  • SSC Study Materials
  • SSC CAPF
  • SSC CGL
  • SSC CHSL
  • SSC MTS
  • SSC Steno C and D
  • Role of Agriculture in the Indian Economy
  • Unification of Italy
  • Nature of Indian Economy
freeliveclasses_ssc

Related links

  • Parliament of India-Vidhan Sabha and Vidhan Parishad
  • Semantic Series
  • The Indian Subcontinent: Position, Extent and Physical Features
testseries_ssc
Download SSC Notes
. document.querySelector('.targetTopBtn').onClick = topFunction; function topFunction() { window.scrollTo({ top: 0, behavior: 'smooth' }) }
Company Logo

Unacademy is India’s largest online learning platform. Download our apps to start learning


Starting your preparation?

Call us and we will answer all your questions about learning on Unacademy

Call +91 8585858585

Company
About usShikshodayaCareers
we're hiring
BlogsPrivacy PolicyTerms and Conditions
Help & support
User GuidelinesSite MapRefund PolicyTakedown PolicyGrievance Redressal
Products
Learner appLearner appEducator appEducator appParent appParent app
Popular goals
IIT JEEUPSCSSCCSIR UGC NETNEET UG
Trending exams
GATECATCANTA UGC NETBank Exams
Study material
UPSC Study MaterialNEET UG Study MaterialCA Foundation Study MaterialJEE Study MaterialSSC Study Material

© 2025 Sorting Hat Technologies Pvt Ltd

Unacademy
  • Goals
    • AFCAT
    • AP EAMCET
    • Bank Exam
    • BPSC
    • CA Foundation
    • CAPF
    • CAT
    • CBSE Class 11
    • CBSE Class 12
    • CDS
    • CLAT
    • CSIR UGC
    • GATE
    • IIT JAM
    • JEE
    • Karnataka CET
    • Karnataka PSC
    • Kerala PSC
    • MHT CET
    • MPPSC
    • NDA
    • NEET PG
    • NEET UG
    • NTA UGC
    • Railway Exam
    • SSC
    • TS EAMCET
    • UPSC
    • WBPSC
    • CFA

Share via

COPY