Access free live classes and tests on the app
Download
+
Unacademy
  • Goals
    • AFCAT
    • AP EAMCET
    • Bank Exam
    • BPSC
    • CA Foundation
    • CAPF
    • CAT
    • CBSE Class 11
    • CBSE Class 12
    • CDS
    • CLAT
    • CSIR UGC
    • GATE
    • IIT JAM
    • JEE
    • Karnataka CET
    • Karnataka PSC
    • Kerala PSC
    • MHT CET
    • MPPSC
    • NDA
    • NEET PG
    • NEET UG
    • NTA UGC
    • Railway Exam
    • SSC
    • TS EAMCET
    • UPSC
    • WBPSC
    • CFA
Login Join for Free
avtar
  • ProfileProfile
  • Settings Settings
  • Refer your friendsRefer your friends
  • Sign outSign out
  • Terms & conditions
  • •
  • Privacy policy
  • About
  • •
  • Careers
  • •
  • Blog

© 2023 Sorting Hat Technologies Pvt Ltd

  • CAT 2023
  • Study Materials
  • Notifications
  • CAT Syllabus
  • CAT Mock Test
  • CAT Exam Pattern
  • CAT Question Paper
  • CAT Preparation Books
  • Downloads
  • Important Formulas
  • Eligibility Criteria
CAT 2025 » CAT Study Material » Data Interpretation and Logical Reasoning » Overview on Critical Path
scholarship_cat

Overview on Critical Path

In this article we are going to learn about Overview on Critical Path, Critical path in project, Critical path analysis, Critical path example and many more things.

Table of Content
  •  

The critical path approach of project management aids in identifying days when extra time can be spent on non-essential aspects of the project. So even if there are delays in some areas, the project can still be completed on time without affecting anyone else.

What is a critical path?

A critical path is a series of interconnected actions or tasks that must be accomplished in order for the project to be finished. It is the longest path from project start to finish (i.e. the path with the longest duration). At the same time, the shortest path represents the quickest way to complete a task. The entire project will be delayed if one of the path’s operations is delayed.

By visualising tasks and activities in a network diagram, such as a Gantt chart, the critical path method (CPM) is a particularly useful tool for scheduling tasks and keeping track of activities. Activities are represented as a network of arrows connecting two event nodes in this graphic. In order to create a functioning network of events and activities, all associated activities must be properly specified. The critical path technique allows for adjustments during the project’s execution, which is one of its most significant advantages.

Flexibility Time and Float

CP is a method for reducing the risk of failure and determining where the project manager has and does not have decision-making flexibility.

In this context, a flexible decision means that some tasks can be started earlier or later without jeopardising the project’s completion date, allowing the project manager to manipulate and adjust the project schedule based on the time between the earliest start date and the latest end date of each activity. That period is more commonly referred to as “float” or “slack” than “flexibility time.” An action with float time is not included in the critical route by definition.

If an activity has one month of float time, it will not be included in the critical path if it begins after the other successors have completed or begun, unless it is required to begin earlier due to an unexpected change in project scope or other factors.

Critical Path Method Definition

The Critical Path Method (CPM) is a scheduling technique that uses network analysis to anticipate job length. The CPM is a set of processes and methodologies used in complex projects to identify and sequence the activities (critical path) that have the greatest impact on the project’s due date, schedule the time required to complete them, and create the predecessor-successor link between them.

In project management, the critical path method employs network diagrams to help decision makers see how long each task will take. CPM is critical for anticipating task timelines, and project managers can use it in conjunction with activity network diagrams to:

Schedule the amount of time each task or event will take (duration).

Combine the durations of all actions into a timeline for analysis.

Determine how each activity affects the project’s progress.

Make appropriate team assignments for key tasks.

Visualizing the Critical Path with an Activity Network Diagram

As previously said, using an activity network diagram is one of the greatest strategies to assure good project planning and scheduling. Planners can more easily visualise and specify the important activity path with such a model.

Teams use network diagrams to visualise the complete work, which is divided down into interdependent tasks, and to plan their next steps. Bubbles, boxes, and arrows will aid with understanding the activities and their relationships. The diagram is created by the project manager to model the flow of activities and show the critical path specification. Each activity is identified by a code (ID) or a name, and activity pathways must be highlighted. Here’s an example:

MS Excel Spreadsheet for CP Method Example

You have a complete list of all actions to be completed inside your designated project, from start to finish, in your work breakdown structure. Your objective is to determine the duration and predecessor(s) of each action before attempting to construct a network diagram. You can add activities to your critical sequence that have no float time and must be finished on time.

Spreadsheet software can be used to evaluate and visualise the critical path in project management. You can, for example, use MS Excel to construct a spreadsheet that contains all of your project activities, including their ID, duration, predecessors, and successors. MS Project, on the other hand, provides more capabilities for establishing and analysing critical routes in projects.

Conclusion

Critical path was designed with the intention of estimating work time and assisting each of these behind-schedule projects in regaining control. The critical path method is now widely used to identify the most vital tasks and ensure that your project stays on track.

faq

Frequently asked questions

Get answers to the most common queries related to the CAT Examination Preparation.

What kind of graphic is used to show the critical path?

Answer: A Gantt Chart is frequently used to depict a critical path. It begins with activity 1 and continues until ac...Read full

Is it possible for there to be more than one crucial path?

Answer: In a project schedule, there can only be one critical path: a sequence of activities with no float time that...Read full

What criteria do you use to select the critical path?

Answer: You can use a network diagram to display your project’s activity list and durations once you have them...Read full

Is float possible on a critical path?

Answer: If the float time for each activity is less than a week, it can be removed off the critical route and added ...Read full

Is critical path analysis applicable to any project?

Answer: The CP approach can be applied to any project in which several tasks must be accomplished within a specific ...Read full

Answer: A Gantt Chart is frequently used to depict a critical path. It begins with activity 1 and continues until activity n is completed. Interdependent activities can be shown using network diagrams.

Answer: In a project schedule, there can only be one critical path: a sequence of activities with no float time that runs from start to completion.

 

Answer: You can use a network diagram to display your project’s activity list and durations once you have them. You can tell which actions are on the critical route and which aren’t (they’re off the critical path) by glancing at the diagram. This will help you better plan your project and keep track of its development.

Answer: If the float time for each activity is less than a week, it can be removed off the critical route and added to your extended float time once you’ve found the activity with the longest length.

Answer: The CP approach can be applied to any project in which several tasks must be accomplished within a specific time range. It can be applied to IT, engineering, construction, marketing, and operations projects.

Crack CAT with Unacademy

Get subscription and access unlimited live and recorded courses from India’s best educators

  • Structured syllabus
  • Daily live classes
  • Ask doubts
  • Tests & practice
Learn more

Notifications

Get all the important information related to the CAT Exam including the process of application, important calendar dates, eligibility criteria, exam centers etc.

CAT Eligibility Criteria 2023
CAT Exam Pattern 2023
CAT Result 2022
CAT Syllabus 2023 – CAT Exam Syllabus – Download Latest PDF
IBSAT 2022 Notification
IIFT Notification
MAH CET Notification
MICAT Notification
NMAT Notification
SNAP Notification
TISSNET Notification
Top Colleges in India That Accept CAT Score
XAT Notification
See all

Related articles

Learn more topics related to Data Interpretation and Logical Reasoning
Wilson Remainder Theorem

To reduce huge numbers with regard to a certain modulus and to solve congruences, Wilson's theorem and Fermat's theorem can be employed.

Why Use the Critical Path Method

A brief note on Why use the critical path method, Improves future planning, Facilitates more effective resource management, Helps avoid bottlenecks and many things.

What is Types of Analogy Reasoning

In this lecture we’re going to learn about types of analogy reasoning, the number based/numerical analogy, letter and number based analogy and general knowledge-based analogy, questions based on analogy and many more things.

What is Posterior Probability

A posterior probability, in Bayesian records, is the revised or updated probability of an event happening after taking into account new records. The posterior probability is calculated by updating the prior probability by using Bayes’ theorem. In statistical phrases, the posterior probability is the probability of event A taking place given that event B has taken place.

See all
Access more than

469+ courses for CAT – Optional

Get subscription

Trending Topics

  • CAT Mock Test
  • CAT Question Papers
  • CAT 2021 Question Paper
  • CAT 2020 Question Paper
  • CAT Question Paper 2019 PDF
  • Best Books for CAT Preparation
  • CAT Eligibility Criteria
  • CAT Syllabus
  • CAT Exam Pattern
  • CAT Result
combat_cat

Related links

  • Co-ordinate Geometry applications
  • What Is A Polygon?
  • Uses of a Quadrilateral
  • Algebraic Identities
  • SPSS Full Form
  • Geometric Progression’s Uses
  • Blood Relation Questions
freeliveclasses_cat
CAT 2024 Question Paper
.
Company Logo

Unacademy is India’s largest online learning platform. Download our apps to start learning


Starting your preparation?

Call us and we will answer all your questions about learning on Unacademy

Call +91 8585858585

Company
About usShikshodayaCareers
we're hiring
BlogsPrivacy PolicyTerms and Conditions
Help & support
User GuidelinesSite MapRefund PolicyTakedown PolicyGrievance Redressal
Products
Learner appLearner appEducator appEducator appParent appParent app
Popular goals
IIT JEEUPSCSSCCSIR UGC NETNEET UG
Trending exams
GATECATCANTA UGC NETBank Exams
Study material
UPSC Study MaterialNEET UG Study MaterialCA Foundation Study MaterialJEE Study MaterialSSC Study Material

© 2025 Sorting Hat Technologies Pvt Ltd

Unacademy
  • Goals
    • AFCAT
    • AP EAMCET
    • Bank Exam
    • BPSC
    • CA Foundation
    • CAPF
    • CAT
    • CBSE Class 11
    • CBSE Class 12
    • CDS
    • CLAT
    • CSIR UGC
    • GATE
    • IIT JAM
    • JEE
    • Karnataka CET
    • Karnataka PSC
    • Kerala PSC
    • MHT CET
    • MPPSC
    • NDA
    • NEET PG
    • NEET UG
    • NTA UGC
    • Railway Exam
    • SSC
    • TS EAMCET
    • UPSC
    • WBPSC
    • CFA

Share via

COPY