Access free live classes and tests on the app
Download
+
Unacademy
  • Goals
    • AFCAT
    • AP EAMCET
    • Bank Exam
    • BPSC
    • CA Foundation
    • CAPF
    • CAT
    • CBSE Class 11
    • CBSE Class 12
    • CDS
    • CLAT
    • CSIR UGC
    • GATE
    • IIT JAM
    • JEE
    • Karnataka CET
    • Karnataka PSC
    • Kerala PSC
    • MHT CET
    • MPPSC
    • NDA
    • NEET PG
    • NEET UG
    • NTA UGC
    • Railway Exam
    • SSC
    • TS EAMCET
    • UPSC
    • WBPSC
    • CFA
Login Join for Free
avtar
  • ProfileProfile
  • Settings Settings
  • Refer your friendsRefer your friends
  • Sign outSign out
  • Terms & conditions
  • •
  • Privacy policy
  • About
  • •
  • Careers
  • •
  • Blog

© 2023 Sorting Hat Technologies Pvt Ltd

  • CAT 2023
  • Study Materials
  • Notifications
  • CAT Syllabus
  • CAT Mock Test
  • CAT Exam Pattern
  • CAT Question Paper
  • CAT Preparation Books
  • Downloads
  • Important Formulas
  • Eligibility Criteria
CAT 2025 » CAT Study Material » Data Interpretation and Logical Reasoning » Compress Schedules
scholarship_cat

Compress Schedules

All about Compress schedules, Two schedule compression techniques, Fast tracking, Crashing and many things.

Table of Content
  •  

Schedule compression techniques are ways to cut the time it takes to finish a project while keeping its scope and quality the same. This can be done by taking out tasks, activities, or phases from the project schedule that aren’t needed or by finishing tasks in less time than was planned. When a project manager wants to shorten the length of a project without changing its scope, they use techniques called “schedule compression.” It can be used when a project is behind schedule and needs to catch up, or when it needs to be finished earlier than planned.

What Is a Compressed Schedule?

When making a schedule, if a project is behind schedule, schedule compression techniques are used. The goal of schedule compression is to try to get more done in less time without changing the scope of the project. Because if the scope of a project hasn’t changed and the project is behind schedule, the only way to meet the original deadline is to shorten the remaining schedule.

Two schedule compression techniques

The first way to shorten a project’s schedule is called “fast tracking.”

The first method is called “fast tracking.” Let’s talk about what fast tracking means in project management. In the fast tracking schedule compression technique, activities on the critical path are done at the same time instead of one after the other. This is possible as long as the tasks don’t have to be done in a certain order. Because if two things depend on each other by their very nature, you can’t do them both at the same time. For example, you can’t start testing a screen before it’s finished being built. If two critical path activities depend on each other because of a resource dependency or a choice dependency, you can move those activities to the front of the line so you can finish the other tasks faster.

The second way to shorten a project’s schedule is called “crashing.”

The second method is to crash. In the crashing schedule compression technique, cost and time are traded off. If the project is behind schedule and the scope hasn’t changed, one way to get it back on track is to put more resources on the remaining tasks. Because if more than one resource can be assigned to an activity, it will take less time to do that activity. This will help get the project done more quickly. But since these extra resources weren’t part of the original plan, using crashing to compress the schedule will cost more.

5 major steps to follow if the project is behind the schedule

If a project is behind schedule, there are 5 big steps that need to be taken in order.

• First, check and re-evaluate the risks. Because re-estimating the remaining activities can lead to shorter activity times if the risks that were taken into account during planning are no longer true. Re-estimating will show how long it will take to finish the rest of the project’s tasks.

• If re estimating the project causes the deadline to be pushed back, the project should be sped up. The remaining critical path activities are looked at, and any tasks that can be done at the same time can be done to speed up the project. This is one of the advantages of fast tracking over crashing in project management, since fast tracking doesn’t cost the project any more money.

• Stopping the project is the third step. To cover the rising costs, plans are made for more resources and more money is set aside. Since more people will work on the project’s remaining tasks, it should be possible to finish on time.

• Scope reduction is the fourth step. Reducing the project’s scope can help cut down on the number of tasks left to do, and if the customer agrees, it can help the project get done on time.

• Cutting the quality is the fifth step. To reach a certain level of quality, you have to spend money and spend time. If the customer agrees to accept less quality, you can finish the project faster by cutting back on quality. Note that the fourth and fifth steps are not the best way to go about a project.

Conclusion

Project managers start with fast-tracking because it doesn’t cost more and helps them get more done in less time. But it increases risk because things are happening at the same time. As a general rule, you can speed up activities that come one after the other by 33%. This means that you can move on to the next task when the last one is 66 percent done.

faq

Frequently asked questions

Get answers to the most common queries related to the CAT Examination Preparation.

How do I compress a project timeline?

Ans. Project managers start with fast-tracking because it doesn’t cost more and helps them get more done in le...Read full

What are two reasons you may need to compress a project time schedule?

Ans. Fast Tracking and Crashing are used when a project is behind schedule and needs to get back on track, or when t...Read full

Why does project cost increase when schedule is compressed?

Ans. It means adding more physical and human resources to the Critical Path Activities or making changes to them so ...Read full

How is CPM different from CCM?

Ans. PMBOK says that CPM is “a method used to estimate the minimum project duration and figure out how much sc...Read full

What are the risks associated with compressing or crashing a project?

Ans. Compressing is a method for shortening a previously set schedule without reducing the size or scope of a projec...Read full

Ans. Project managers start with fast-tracking because it doesn’t cost more and helps them get more done in less time. But it increases risk because things are happening at the same time. As a general rule, you can speed up activities that come one after the other by 33%. This means you can move on to the next task when the last one is 66 percent done.

Ans. Fast Tracking and Crashing are used when a project is behind schedule and needs to get back on track, or when the length of the project needs to be cut down. Unrealistic plan for the schedule. It took too long to get the resources.

Ans. It means adding more physical and human resources to the Critical Path Activities or making changes to them so that the project can be finished faster without changing the Original Project Scope. It may save money and shorten the time it takes to finish a project, but it always leads to higher costs because more resources are needed.

Ans. PMBOK says that CPM is “a method used to estimate the minimum project duration and figure out how much scheduling flexibility there is on the logical network paths within the schedule model.”” while “CCM is a scheduling method that lets the project team add buffers to any project schedule path to account for limited resources.”

Ans. Compressing is a method for shortening a previously set schedule without reducing the size or scope of a project. When a schedule is compressed, there is a chance that time will run out and that one or more activities in the network may have to be cut.

Crack CAT with Unacademy

Get subscription and access unlimited live and recorded courses from India’s best educators

  • Structured syllabus
  • Daily live classes
  • Ask doubts
  • Tests & practice
Learn more

Notifications

Get all the important information related to the CAT Exam including the process of application, important calendar dates, eligibility criteria, exam centers etc.

CAT Eligibility Criteria 2023
CAT Exam Pattern 2023
CAT Result 2022
CAT Syllabus 2023 – CAT Exam Syllabus – Download Latest PDF
IBSAT 2022 Notification
IIFT Notification
MAH CET Notification
MICAT Notification
NMAT Notification
SNAP Notification
TISSNET Notification
Top Colleges in India That Accept CAT Score
XAT Notification
See all

Related articles

Learn more topics related to Data Interpretation and Logical Reasoning
Wilson Remainder Theorem

To reduce huge numbers with regard to a certain modulus and to solve congruences, Wilson's theorem and Fermat's theorem can be employed.

Why Use the Critical Path Method

A brief note on Why use the critical path method, Improves future planning, Facilitates more effective resource management, Helps avoid bottlenecks and many things.

What is Types of Analogy Reasoning

In this lecture we’re going to learn about types of analogy reasoning, the number based/numerical analogy, letter and number based analogy and general knowledge-based analogy, questions based on analogy and many more things.

What is Posterior Probability

A posterior probability, in Bayesian records, is the revised or updated probability of an event happening after taking into account new records. The posterior probability is calculated by updating the prior probability by using Bayes’ theorem. In statistical phrases, the posterior probability is the probability of event A taking place given that event B has taken place.

See all
Access more than

469+ courses for CAT – Optional

Get subscription

Trending Topics

  • CAT Mock Test
  • CAT Question Papers
  • CAT 2021 Question Paper
  • CAT 2020 Question Paper
  • CAT Question Paper 2019 PDF
  • Best Books for CAT Preparation
  • CAT Eligibility Criteria
  • CAT Syllabus
  • CAT Exam Pattern
  • CAT Result
combat_cat

Related links

  • Co-ordinate Geometry applications
  • What Is A Polygon?
  • Uses of a Quadrilateral
  • Algebraic Identities
  • SPSS Full Form
  • Geometric Progression’s Uses
  • Blood Relation Questions
freeliveclasses_cat
CAT 2024 Question Paper
.
Company Logo

Unacademy is India’s largest online learning platform. Download our apps to start learning


Starting your preparation?

Call us and we will answer all your questions about learning on Unacademy

Call +91 8585858585

Company
About usShikshodayaCareers
we're hiring
BlogsPrivacy PolicyTerms and Conditions
Help & support
User GuidelinesSite MapRefund PolicyTakedown PolicyGrievance Redressal
Products
Learner appLearner appEducator appEducator appParent appParent app
Popular goals
IIT JEEUPSCSSCCSIR UGC NETNEET UG
Trending exams
GATECATCANTA UGC NETBank Exams
Study material
UPSC Study MaterialNEET UG Study MaterialCA Foundation Study MaterialJEE Study MaterialSSC Study Material

© 2025 Sorting Hat Technologies Pvt Ltd

Unacademy
  • Goals
    • AFCAT
    • AP EAMCET
    • Bank Exam
    • BPSC
    • CA Foundation
    • CAPF
    • CAT
    • CBSE Class 11
    • CBSE Class 12
    • CDS
    • CLAT
    • CSIR UGC
    • GATE
    • IIT JAM
    • JEE
    • Karnataka CET
    • Karnataka PSC
    • Kerala PSC
    • MHT CET
    • MPPSC
    • NDA
    • NEET PG
    • NEET UG
    • NTA UGC
    • Railway Exam
    • SSC
    • TS EAMCET
    • UPSC
    • WBPSC
    • CFA

Share via

COPY