Sign up now
to enroll in courses, follow best educators, interact with the community and track your progress.
Enroll
753
Download
DI-3_Tables -2
503 plays

More
Solving Tables in Data Interpretation

Venkatesan S
IIM Bangalore Alumni | Cleared CAT 2015 | Cleared IIM B, C, L, K & I

U
Unacademy user
please sir'' will you make course on kinematics previous year paper analysis sir please make in this month i will be thankful sir if you make thiis course sir
Ashok
5 months ago
I will upload it very soon dear
Harsh Jain
5 months ago
thank u sir
sir in 4 question.do we have to take total of material and labour Becoz u took 175
  1. Data Interpretation Basics Video 3-Tables 2 Venkatesan S IIMB Alumni


  2. The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places. 1) The total expenditure is required to be kept within Rs. 700 lakh by cutting th administration equally in all the years. What will be the percentage cut for 1989? e expenditure on 1989 7.5 95.0 70.0 15.0 25.0 1990 2.2 80.0 45.0 12.0 18.0 1991 0.5 75.0 60.0 16.0 21.0 1988 1. Surveying 2. Cement 3. Steel 4. Bricks 41.5 (a) 22.6 (b) 32.6 (c) 42.5 (d) 52.6 2) If the length of line to be laid each year is in proportion to the estimated cost for material and labour, what fraction of the total length is proposed to be completed by the third year? 5. Other building material 25.0 15.0 15.0 267.5 6. Labour 2.1 20.0 18.0 (a) 0.9 (b) 0.7 (c) 0.6 (d) 0.3 15.0 7. Administration 8. Contingencies Total 7.5 14.0 1.0 4.2 5.0 52.1 196.4 209.5


  3. 3) What is the approximate ratio of the total cost of materials for all the years bear to the total labour cost? The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places. 1989 7.5 95.0 70.0 15.0 25.0 1990 2.2 80.0 45.0 12.0 18.0 1991 0.5 75.0 60.0 16.0 21.0 1988 1. Surveying 2. Cement 3. Steel 4. Bricks 5. Other 41.5 (a) 4 1 (b) 8: 1 (c) 12:1 (d) 16:1 4) If the cost of materials rises by 5% each year from 1990 onwards, by how much will the estimated cost rise? (a) Rs. 11.4 lakh (b) Rs. 16.4 lakh (c) Rs.21.4 lakh (d) mlerial Rs.26.4 lakh 6. Labour 7. Administration 8. Contingencies Total 2.1 7.5 1.0 52.1 25.0 15.0 15.0 267.5 20.0 18.0 15.0 14.0 4.2 5.0 196.4 209.5


  4. The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places. 5) It is found at the end of 1990, that the entire amount estimated for the project has been spent. If for 1991, the actual amount spent was equal to that which was estimated, by what percent (approximately) has the actual expenditure exceeded the estimated expenditure? 1989 7.5 95.0 70.0 15.0 25.0 1990 2.2 80.0 45.0 12.0 18.0 1991 0.5 75.0 60.0 16.0 21.0 1988 1. Surveying 41.5 2. Cement 3. Steel (a) 39 (b) 29 (c) 19 (d) 9 4. Bricks 5. Other building material 6. Labour 7. Administration 8. Contingencies Total 6) After preparing the estimate, the provision for contingencies is felt inadequate and is therefore doubled. By what percent does the total estimate increase? 25.0 15.0 15.0 267.5 2.1 20.0 18.0 7.5 15.0 14.0 (a) 3.47 (b) 2.45 (c) 1.50 (d) 3.62 1.0 4.2 5.0 52.1 196.4 209.5


  5. The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places. 1) The total expenditure is required to be kept within Rs. 700 lakh by cutting th administration equally in all the years. What will be the percentage cut for 1989? e expenditure on 1989 7.5 95.0 70.0 15.0 25.0 1990 2.2 80.0 45.0 12.0 18.0 1991 0.5 75.0 60.0 16.0 21.0 1988 1. Surveying 2. Cement 3. Steel 4. Bricks 41.5 (a) 22.6 (b) 32.6 (c) 42.5 (d) 52.6 320 209.5 196 725.5 25.5/4-6.4 6.4/15 40.X 5. Other building material 2.1 7.5 1.0 52.1 25.0 15.0 15.0 267.5 6. Labour 20.0 18.0 15.0 7. Administration 8. Contingencies Total 14.0 4.2 5.0 196.4 209.5


  6. The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places. 2) If the length of line to be laid each year is in proportion to the estimated cost for material and labour, what fraction of the total length is proposed to be completed by the third year? 1989 7.5 95.0 70.0 15.0 25.0 1990 2.2 80.0 45.0 12.0 18.0 1991 0.5 75.0 60.0 16.0 21.0 1988 1. Surveying 2. Cement 3. Steel 4. Bricks 41.5 (a) 0.9 (b) 0.7 (c) 0.6 (d) 0.3 Total Mat & Lab 2.1+230+175+190 567.1 Till 3rd year 377.1 % 377.1 / 567.1-"66.x+ 5. Other building material 2.1 7.5 1.0 52.1 25.0 15.0 15.0 267.5 6. Labour 20.0 18.0 15.0 7. Administration 8. Contingencies Total 14.0 4.2 5.0 196.4 209.5


  7. 3) What is the approximate ratio of the total cost of materials for all the years bear to the total labour cost? The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places. 1989 7.5 95.0 70.0 15.0 25.0 1990 2.2 80.0 45.0 12.0 18.0 1991 0.5 75.0 60.0 16.0 21.0 1988 1. Surveying 2. Cement 3. Steel 4. Bricks 41.5 (a) 4 1 (b) 8:1 (c) 12:1 (d) 16:1 Total Lab & mat 567.1 Total Lab 65.1 5. Other building material Total Mat 502 2.1 7.5 1.0 52.1 25.0 15.0 15.0 267.5 6. Labour 20.0 18.0 15.0 7. Administration 8. Contingencies Total 14.0 4.2 5.0 196.4 209.5


  8. 4) If the cost of materials rises by 5% each year from 1990 onwards, by how much will the estimated cost rise? The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places. 1989 7.5 95.0 70.0 15.0 25.0 1990 2.2 80.0 45.0 12.0 18.0 1991 0.5 75.0 60.0 16.0 21.0 1988 1. Surveying 2. Cement 3. Steel 4. Bricks 41.5 (a) Rs. 11.4 lakh (b) Rs. 16.4 lakh (c) Rs.21.4 lakh (d) Rs.26.4lakh Total Mat cost 502 Mat cost 1989175 Mat cost 337 5%-~16.5 5. Other building material 2.1 7.5 1.0 52.1 25.0 15.0 15.0 267.5 6. Labour 20.0 18.0 15.0 7. Administration 8. Contingencies Total 14.0 4.2 5.0 196.4 209.5


  9. The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places. 5) It is found at the end of 1990, that the entire amount estimated for the project has been spent. If for 1991, the actual amount spent was equal to that which was estimated, by what percent (approximately) has the actual expenditure exceeded the estimated expenditure? 1989 7.5 95.0 70.0 15.0 25.0 1990 2.2 80.0 45.0 12.0 18.0 1991 0.5 75.0 60.0 16.0 21.0 1988 1. Surveying 2. Cement 3. Steel 4. Bricks 41.5 (a) 39 (b) 29 (c) 19 (d) 9 Total Exp Planned 725.5 1991 209.5 New total 935 935/725 5. Other building material 2.1 7.5 1.0 52.1 25.0 15.0 15.0 267.5 6. Labour 20.0 18.0 15.0 7. Administration 8. Contingencies Total 14.0 4.2 5.0 196.4 209.5


  10. The table below shows the estimated cost (in Rs. Lakh) of a project of laying a railway line between two places. 6) After preparing the estimate, the provision for contingencies is felt inadequate and is therefore doubled. By what percent does the total estimate increase? 1989 7.5 95.0 70.0 15.0 25.0 1990 2.2 80.0 45.0 12.0 18.0 1991 0.5 75.0 60.0 16.0 21.0 1988 41.5 (a) 3.47 (b) 2.45 (c) 1.50 (d) 3.62 Contingencies 25.2 Total 725.5 1. Surveying 2. Cement 3. Steel 4. Bricks 5. Other building material 6. Labour 20.0 15.0 4.2 196.4 18.0 2.1 7.5 1.0 52.1 25.0 15.0 15.0 267.5 14.0 7. Administration 8. Contingencies Total 5.0 209.5