Que: A project has six activities (A to F) with respectivr activiy duration 7,5,6,6,8,4 days . The network has three path A-B, C-D,E-F . All the activities can be crashed with the same crash cost per day. The number of activities that need to be crashed to reduce the project duration by 1 day is ? GATE(2005) 2 marks Please sir upload the answer of this question with a good solution
sir from PERT and CPM GATE (2005 ) que i am not able to solve the que.
I will upload soon and please see all vedios along with numerical for CPM and pert