Home
SELF STUDY
BrowsePracticeTestsPlaylistDoubts & solutionsFree live classesOther courses

Engineering Economy

Quick practice

Question 1 of 5

Negative slack on a PERT indicates that project is

A

On critical path

B

Behind schedule

C

As per schedule

D

Ahead of schedule

Get unlimited practice with GATE & ESE - Civil subscription

pick

Boost your performance with adaptive practice tests

pick

Practice every concept in the syllabus

pick

Compare your speed and accuracy with your peers

pick

Download the app and practice on the go