Home
SELF STUDY
BrowsePracticeTestsPlaylistDoubts & solutionsFree live classesOther courses

Inventory Control

Quick practice

Question 1 of 5

Consider a two machine flow shop where jobs are first processed in Machine X and then in Machine Y, in the same sequence. The processing times of four jobs (1, 2, 3 and 4) on the machines are:

The sequence of jobs on the machines that minimizes make span is

A

1-2-3-4

B

3-1-4-2

C

2-3-1-4

D

2-1-3-4

Get unlimited practice with GATE & ESE - ME & CH subscription

pick

Boost your performance with adaptive practice tests

pick

Practice every concept in the syllabus

pick

Compare your speed and accuracy with your peers

pick

Download the app and practice on the go