Consider a two machine flow shop where jobs are first processed in Machine X and then in Machine Y, in the same sequence. The processing times of four jobs (1, 2, 3 and 4) on the machines are:

The sequence of jobs on the machines that minimizes make span is

A

1-2-3-4

B

2-3-1-4

C

3-1-4-2

D

2-1-3-4