Consider a two machine flow shop where jobs are first processed in Machine X and then in Machine Y, in the same sequence. The processing times of four jobs (1, 2, 3 and 4) on the machines are:
The sequence of jobs on the machines that minimizes make span is
1-2-3-4
2-1-3-4
3-1-4-2
2-3-1-4
Boost your performance with adaptive practice tests
Practice every concept in the syllabus
Compare your speed and accuracy with your peers
Download the app and practice on the go