As a chairperson anticipating penalties, what is the most strategically sound next step?
Request a formal extension citing monsoon forecasts and political unrest, without altering internal processes.
Document systemic bottlenecks and propose a joint task force with the Ministry to address land, supply, and clearance issues.
Fast-track construction by bypassing certain local approvals, reducing delays.
Publicly blame the Ministry for unrealistic targets, forcing them to revise their stance.
Reassign project responsibility from mid-level managers to senior officers for tighter control.